July 26, 2021

Order issued to Bruce Power

The CNSC has issued an order to Bruce Power related to the operation of Bruce Nuclear Generating Stations A and B.

The order requires Bruce Power to obtain authorization from the Commission prior to the restart to Units 3, 4, 5, 7 or 8 following any outage that results in the cooldown of the heat transport system.

The order requires the licensee, prior to seeking restart authorization, to complete one of the following:

  • Carry out inspection and maintenance activities and submit results of such activities to CNSC staff that demonstrate with a high degree of confidence that pressure tube hydrogen levels [Heq] are within Bruce Power's licensing basis.

Or

  • Carry out inspection and maintenance activities and submit results of such activities to CNSC staff that demonstrate with a high degree of confidence that no flaws are present in the region of pressure tubes where the models failed to conservatively predict the elevated hydrogen levels [Heq].

Read the order (PDF, 2 pages, 143 kb)