Letter to Ontario Power Generation regarding Regulatory Hold Point 1 – Darlington Unit 3
Regulatory Operations Branch
November 28, 2022
Mr. Richard Geofroy
Senior Vice President, Nuclear
Ontario Power Generation Inc.
1 Holt Road South, P.O. Box 4000
Bowmanville, ON L1C 3Z8
Ms. Subo Sinnathamby
Senior Vice President, Refurbishment
Ontario Power Generation Inc.
1855 Energy Drive, 3C14
Courtice, ON L1E 0E7
Subject: Darlington NGS - Unit 3 Return to Service: Request for CNSC Consent to Remove the Regulatory Hold Point for Prior To Fuel Load
Dear Mr. Geofroy and Ms. Sinnathamby:
The purpose of this letter is to respond to Ontario Power Generation’s (OPG) submission [1], which requests removal of Regulatory Hold Point-1 (RHP-1), allowing fuel to be loaded in the refurbished Darlington Unit 3 reactor core, and provides the associated Completion Assurance Document.
Canadian Nuclear Safety Commission (CNSC) staff’s assessment [2] of OPG’s submission [1], as well as all supporting documentation, concluded that OPG has met all the pre-requisites established by the Commission to remove RHP-1. Therefore, as the person authorized by the Commission and pursuant to Licence Condition 15.4 of the Darlington Nuclear Generating Station (DNGS) Power Reactor Operating Licence 13.03/2025, consent to remove RHP-1 is hereby granted and fuel may now be loaded into the Unit 3 core.
Yours sincerely,
Ramzi Jammal
Executive Vice-President and
Chief Regulatory Operations Officer
Regulatory Operations Branch
c.c: A. Viktorov, J. Burta, M. Rickard, C. Loreti, N. Abonasara, A. Oussoren, C. Badal, C. Brown, C. Chan, Darlington Site Office
References:
- OPG Letter, R. Geofroy and S. Sinnathamby to R. Jammal, “Darlington NGS Refurbishment: Unit 3 Return to Service: Request for CNSC Consent Prior to Fuel Load (RHP1)”, dated November 24, 2022
- CNSC staff document entitled: “Request by Ontario Power Generation Inc. to Remove Regulatory Hold Point for Prior To Fuel Load for Unit 3”, dated November 27, 2022
- CNSC Letter, J. Burta to S. Gregoris and S. Sinnathamby, “Ontario Power Generation Protocol with the Canadian Nuclear Safety Commission for Darlington Nuclear Generating Station Unit 3 Return to Service-Revision 1”, October 19, 2021