Regulatory review status for the decommissioning of the Whiteshell Reactor #1
Canadian Nuclear Laboratories (CNL) is proposing to decommission Whiteshell Reactor #1 (WR-1), using an approach that was not previously assessed when the decommissioning licence was first issued. The WR-1 is a former nuclear research reactor that operated until 1985. It is located at the Whiteshell Laboratories (WL) site in Pinawa, Manitoba, approximately 100 kilometres northeast of Winnipeg, near the towns of Lac du Bonnet and Seven Sisters.
CNL is proposing an in situ (leaving in place) decommissioning approach. In situ decommissioning involves preparing systems and structures for grouting. The below-grade grouted structure will encapsulate and contain radiological sources and hazardous materials for a defined period of institutional control.
The following activities are being proposed:
- preparation for in situ decommissioning
- grouting of below-grade (underground) structures and systems
- removal of above-grade (above-ground) structures and systems
- installation of engineered cover over grouted area
- final site restorations
- long-term care and maintenance activities
Some temporary infrastructure – such as construction trailers and equipment paddocks, as well as an increase to the electrical services – would also be required in order to facilitate decommissioning. Additional groundwater monitoring wells would be installed, as required, to monitor the performance of the in situ decommissioned facility.
This proposal requires authorization by the Canadian Nuclear Safety Commission (CNSC) in the form of an amended licence. Under the Nuclear Safety and Control Act (NSCA), CNL must apply to the Commission to amend the current decommissioning licence and undergo a review. However, before the Commission can make a licensing decision on this proposal, CNSC staff must complete an environmental assessment (EA) under the Canadian Environmental Assessment Act, 2012 (CEAA 2012).
Although the Impact Assessment Act came into force August 28, 2019, it contains provisions for ongoing projects to be completed under CEAA 2012 . This means that the CNSC will continue to lead the review of this project.
The completion of an EA under CEAA 2012 involves producing an EA report based on the information in CNL’s licensing submission, a final environmental impact statement (EIS) and other supporting documentation.
CNSC’s environmental assessment process
CNSC staff must have reviewed enough evidence and be able to show that the proposed activities would not cause significant adverse environmental effects, before the Commission can proceed with its decision. The CNSC will make this information available as Commission member documents before a public hearing, to be scheduled at a later date.
Environmental assessment start date: March 16, 2016
Reference number: 80124
Timeline
Application submitted |
|
---|---|
Date | Activity |
April 23, 2002 | CNL submits and CNSC starts review of licence application |
Assessments |
|
---|---|
Date | Activity |
May 16, 2016 | Notice of commencement of the EA |
June 2, 2016 | Public comments invited on project description |
June 3, 2016 | Notice of participant funding offering |
March 8, 2017 | Record of decision on the scope of the EA |
September 1, 2017 | CNL submission of licensing documentation |
October 5, 2017 | Public comments invited on draft EIS |
October 17, 2017 | CNSC open houses (Winnipeg, Pinawa and Lac du Bonnet) |
January 5, 2018 | Review of CNL’s draft EIS completed |
April 3, 2018 | Update on the status of the EA process |
April 30, 2020 | CNL submission of revised draft EIS and responses to federal and provincial information requests deemed incomplete |
August 24, 2022 | CNL submission of revised draft EIS and responses to federal and provincial information requests deemed incomplete |
January 16, 2023 | CNSC technical review of EIS and licence application |
April 27, 2023 | Review team completes technical review of revised EIS |
May 8, 2023 | Review team completed technical review of EIS (including findings from Sagkeeng First Nation) |
To be confirmed | Review team completes technical review of revised EIS |
To be confirmed | CNL submission of final EIS and licence documentation |
To be confirmed | CNSC staff Commission member document and EA report available for public review |
To be confirmed | Public intervention deadline |
To be confirmed | Commission hearing for EA and licensing decisions |
To be confirmed | Commission decision announcement |
Public hearing |
|
---|---|
Date | Activity |
To be confirmed |
Commission decisions |
|
---|---|
Date | Activity |
To be confirmed |
Licence issued |
|
---|---|
Date | Activity |
To be confirmed |
Compliance activities |
|
---|---|
Date | Activity |
To be confirmed |
Contact
For general CNSC updates, subscribe to the CNSC’s mailing list. For information directly related to this project, please contact:
Aimee Rupert, Environmental Assessment Officer
Email: WR1@cnsc-ccsn.gc.ca
Telephone: 613-316-2087 or 1-800-668-5284
Mailing address: Canadian Nuclear Safety Commission
P. O. Box 1046, Station B
Ottawa, ON K1P 5S9
Additional resources
Page details
- Date modified: