Regulatory review status of Nuclear Power Demonstration Closure Project
Canadian Nuclear Laboratories (CNL) is proposing to decommission the Nuclear Power Demonstration (NPD) waste facility, a former nuclear generating station that operated until 1987. The facility is located in Renfrew County, Ontario, on the south bank of the Ottawa River approximately 225 km northwest of Ottawa.
The structures that remain onsite include the main reactor building, a diesel generator, a ventilation stack, a pressure relief duct, a guardhouse, foundations from previously removed structures, 2 landfills, buried utilities and drainage systems, and temporary structures such as sea containers and portable washrooms.
CNL is proposing an in situ (leaving in place) decommissioning approach. The following activities are proposed:
- assembly and operation of a grout batch mixing plant
- grouting of below-grade (underground) structures
- removal of above-grade structures for use as backfill
- installation of concrete cap and engineered barrier over the grouted area
- final site restoration
- long-term care and maintenance activities
Some temporary infrastructure – such as mobile offices and washrooms, as well as an increase to electrical services – would be required in order to facilitate decommissioning. Water-holding tanks and fuel storage may also be needed onsite to support the proposed project. Additional groundwater monitoring wells would be installed, as required, to monitor the performance of the in situ decommissioned facility.
The proposed NPD Closure Project requires authorization by the Canadian Nuclear Safety Commission (CNSC) in the form of a licence, and must undergo a review pursuant to the Nuclear Safety and Control Act in order to proceed. CNL is seeking CNSC approval for a licence amendment to the current NPD waste facility decommissioning licence. However, before the Commission can make a licensing decision on this proposal, CNSC staff must complete an environmental assessment (EA) under the Canadian Environmental Assessment Act, 2012 (CEAA 2012). Although the Impact Assessment Act came into force on August 28, 2019, it contains provisions for ongoing projects to be completed under CEAA 2012. This means that the CNSC will continue to lead the review of the NPD Project.
The completion of an EA under CEAA 2012 involves producing an EA report based on the information in CNL’s project description, final environmental impact statement (EIS) and other supporting documentation.
The CNSC's environmental assessment process
CNSC staff must review the evidence and provide information on whether the proposed NPD Closure Project is likely to cause significant adverse environmental effects before the Commission can proceed with its licensing decision. The CNSC will make this information available as a Commission member document (CMD) before Part 1 of the 2-part public hearing.
Environmental assessment start date: May 5, 2016
Reference number: 80121
Timeline
Application submitted |
|
---|---|
Date | Activity |
May 5, 2016 | CNL submission of licence application to amend current waste facility decommissioning licence |
Public hearing |
|
---|---|
Date | Activity |
To be confirmed |
Commission decisions |
|
---|---|
Date | Activity |
To be confirmed |
Licence issued |
|
---|---|
Date | Activity |
To be confirmed |
Compliance activities |
|
---|---|
Date | Activity |
To be confirmed |
Contact
For general CNSC updates, subscribe to the CNSC’s mailing list. For information directly related to this project, please contact:
Veronica Mossop, Environmental Assessment Officer
Email: npd@cnsc-ccsn.gc.ca
Telephone: 343-542-7469 or 1-800-668-5284
Mailing address: Canadian Nuclear Safety Commission
P. O. Box 1046, Station B
Ottawa, ON K1P 5S9
Additional resources
- Canadian Impact Assessment Registry on the Nuclear Power Demonstration Closure project
- Canadian Nuclear Laboratories Nuclear Power Demonstration Closure Project
- Administrative protocol between Canadian Nuclear Laboratories and the CNSC for the Nuclear Power Demonstration Closure Project (Revision 2 – July 2020) Appendix A – EA Timelines (Revision 4, July 2020)
Page details
- Date modified: