The Midwest Mining and Milling Project
The Impact Assessment Act (IAA) came into force August 28, 2019. Ongoing projects with environmental assessments initiated under the Canadian Environmental Assessment Act, 2012 (CEAA 2012) and led by the CNSC, will continue under their current processes. The IAA contains provisions to enable these projects to advance in this way.
Location: McClean Lake, Saskatchewan
Summary: The Midwest Project involves the mining and milling of a uranium deposit located near the eastern margin of the Athabasca basin in northern Saskatchewan; about 15 km west of the JEB mill at the McClean Lake Operation. The project is proposed as an extension of the mining and milling activities at the McClean Lake Operation.
Environmental and licensing progress details: (Timelines are best estimates and are subject to change)
- Environmental assessment, site preparation site and construct (Last updated: January 10, 2011)
- Operation
- Decommissioning
Project milestone | Responsibility and status | Date | Comment | |
---|---|---|---|---|
CNSC and other federal authorities | Applicant | |||
Areva licence application and project description (PDF) (source: MPMO) | Completed by AREVA | December 28, 2005 |
| |
Final environmental impact statement (EIS) guidelines (source: Saskatchewan Environment) | Completed by the federal Minister of Environment | October, 2007 | Finalized by the federal Minister of the Environment, in consultation with the President of the CNSC, based on comments received. | |
Receipt of initial EIS to support the application to amend the McClean Lake operating licence to construct the project. | Completed by AREVA | October 22, 2007 to March 2008 | Was received in three parts (Oct 2007, Jan 2008, and March 2008) | |
Project brought in under the Major Projects Management Office (MPMO) Initiative | Completed by MPMO | February 26, 2009 | ||
Completed by the CNSC | April 30, 2009 | The Commission decided to renew the McClean Lake operating licence. The ommission also revoked the Midwest Uranium site preparation licence and included it in McClean Lake licence. | ||
MPMO project agreement signed Project Agreement for the Midwest Uranium Mining and Milling Project in Saskatchewan (source: MPMO) | Completed by MPMO | December 2009 | An MPMO project agreement is an agreement between federal Deputy Ministers that outlines the process by which federal government departments or agencies will carry out their particular roles or responsibilities during the federal regulatory review of a proposed major resource project. The agreement includes a timeline and schedule for the completion of the regulatory review with regular milestones to allow tracking of progress. | |
AREVA submits revised EIS | Completed by AREVA | February 26, 2010 | ||
Federal review of revised EIS and fish habitat compensation plan | Completed Lead by CEAA | February 27 to April 28, 2010 | ||
Federal request to AREVA to revise EIS | Completed by CEAA | April 2010 | AREVA has been requested to revise the EIS again based on the comments received | |
Federal government posts revised notice of commencement (source: CEAA) | Completed by the CNSC | August 31, 2010 | Per amendments to the CEA Act that came into force with the Jobs and Economic Growth Act in July 2010, the CNSC will lead on the remaining steps of the environmental assessment (source: Department of Justice Canada) | |
AREVA submits final EIS | Completed by AREVA | September 30, 2011 | ||
Prepare draft comprehensive study report (CSR) and circulate for review | Completed by the CNSC, with support from responsible authorities and expert federal authorities | December 5, 2011 | CNSC circulates draft CSR to federal responsible authorities, federal authorities as well discussing a revised CSR with Aboriginal groups. | |
Aboriginal engagement on draft CSR | Completed Led by the CNSC | December 5 to December 30, 2011 | ||
Prepare final CSR and circulate for review | Completed by the CNSC | January 27, 2012 | ||
Approve final CSR | Completed by the responsible authorities | March 16, 2012 | ||
Translate final CSR | Completed Verified by the CNSC | Completed by Translation Services | May 11, 2012 | |
Submit the final CSR to the federal Minister of the Environment | Completed by the CNSC and the responsible authorities | May 18, 2012 | ||
Post Final CSR for public and Aboriginal comments on the Canadian Environmental Assessment Registry Internet site (CEARIS) | Completed by CEAA | May 28, 2012 | ||
Post notice of federal Minister of the Environment decision statement on CEARIS | Completed by CEAA | August 15, 2012 | ||
Post EA course of action decisions on the CEARIS | Completed by the CNSC and the Responsible Authorities | September 12, 2012 | ||
AREVA submits technical information to support the application to amend the McClean Lake operating licence to construct the project. | CNSC | TBD | ||
CNSC review of technical information | CNSC | Within 6 months of receipt of technical information | ||
Notice of public hearings posted | CNSC | TBD | Should the EA decision be that the project is not likely to cause significant adverse environmental effects, the panel of the Commission will conduct hearings on the application for amendment, in accordance with the NSCA and its Rules of Procedure – the first step is to issue a Notice of Public Hearing. | |
Conduct day one of two-day hearing | CNSC | TBD | On Hearing Day 1 of a two-day public hearing, the applicant and CNSC staff present written and oral submissions to the Commission and respond to questions from the Commission. | |
Conduct day two of two-day hearing | CNSC | TBD | On Hearing Day 2 registered intervenors have a further opportunity to make their views known to the Commission and to respond to any related questions from the Commission Members. The applicant and CNSC staff must also attend Hearing Day 2 and be prepared to respond to further questioning by the Commission. | |
Publish decision and reasons for decision | CNSC | TBD | The CNSC Commission publishes its final decision, complete with rationale. |